1. Preparatory Phase & Project Initiation (1–2 months)
- Define certification levels:
- ISO 3834: Part 2 / 3 / 4
- EN 1090: Execution Classes EXC 1–4
- EN 15085: Welding Capability Levels CL 1–4
- Select an accredited European Notified Body (NB)
- Sign a combined certification contract
- Establish a project team and provide standard training
- Conduct gap analysis against all three standards
- Develop a gap closure and implementation plan
2. System Establishment & Documentation (2–3 months)
- Build a unified Welding Quality Management System (WQMS) based on ISO 3834
- Develop integrated quality manual, procedures, and work instructions
- Complete WPS / PQR in accordance with EN ISO 15614
- Qualify welders per EN ISO 9606 and welding operators per EN ISO 14732
- Certify NDT personnel at Level 2 (VT/UT/RT/MT) per EN ISO 9712
- Upgrade workshop facilities: welding equipment, welding consumable storage, environmental control, traceability system
- Verify material certificates (3.1 / 3.2)
3. System Trial Run & Internal Audit (2–3 months)
- Operate the system for a minimum of 3 months with real production records
- Conduct internal audits covering ISO 3834, EN 1090, and EN 15085
- Perform management review
- Finalize all welding qualifications and testing documents
- Prepare sample products for on-site audit
4. Combined Document Review (1 month)
Submit full documentation to the certification body:
- Company legal documents
- Welding quality manual and procedures
- Qualifications of welding coordinators, welders, and NDT staff
- WPS / PQR dossiers
- Equipment calibration records
- Factory Production Control (FPC) plan
- EN 1090 ITT (Initial Type Testing) plan
- EN 15085 welding level and component classificationAddress non-conformities and obtain document approval
5. Combined On-Site Audit (3–7 days)
Single on-site audit covering all three standards:
- ISO 3834: Welding quality system, records, traceability, workshop management
- EN 1090: FPC, EXC control, dimensional control, NDT, coating, CE marking, DoP preparation
- EN 15085: CL level control, weld quality classes CPA/B/C/D, railway-specific inspection
- Witness production and testing
- Resolve minor and major non-conformities
6. Corrective Actions & Certification (1–2 months)
- Close all non-conformities
- Undergo technical review by the certification body
- Obtain three certificates simultaneously:
- ISO 3834 Certificate
- EN 1090 Certificate (CE + FPC)
- EN 15085 Certificate
- Certificate validity: 3 years
7. Surveillance & Recertification
- Annual surveillance audit (combined for all three standards)